Route 109 Update for the week of September 18, 2017

Route 109 Update for the week of September 18, 2017

The contractor will continue reclaiming Main Street heading east up to number 133 Main Street.  A second crew will continue installing electrical conduit for the street lights and traffic lights.

A second contractor will be installing foundations for the traffic light bases.