Route 109 Update for the week of August 8, 2016

We understand that there have been some concerns regarding lane closures before 9 a.m.  DPS has reminded the contractor and utilities that they cannot reduce the travel lane to less than two lanes before 9 am. 

Next week work will continue in the east bound lane travelling west up the hill toward Tri-Valley Commons.

Colombia Gas continues work around Choate Pond in the west bound lane.   

Verizon will be working on pole relocations, locations to be determined.   

Full project overview and video here: http://www.townofmedway.org/route-109-transportation-improvement-project