Route 109 Update for the week of August 29, 2016

The contractor will continue to install drainage in the east bound lane heading west as far as Dunkin Donuts.  Thursday they will be cleaning up and paving that section of road. The following week they’ll be moving up toward the Pond Street and Cottage Street areas to start the next section of drainage.

The gas company is just crossing over the yellow center line into the east bound lane on Main Street still heading west installing the new gas main.

Tree removal will continue next week.