Road Paving Update - August 9, 2021
Posted on: August 9, 2021 - 9:47am
The Highway Department reports that paving is scheduled to start TODAY, August 9, and will continue thru Thursday, August 12.
The following roads will receive a binder coat:
Meryl Street, Richard Road, Robin Circle, Beatrice Lane, and Applegate Road.
(What Is the Binder? The binder, which is sometimes called the base coat, is a load-bearing course consisting of aggregate and hot-mix asphalt).
Once the base is complete, they will put the topcoat on the following roads:
Coffee Street, Ellis Street, Virginia Road, Karen Avenue, Gorwin Drive, Douglas Street, Lee Lane, and Carole Lane.
The topcoat will be done on Applegate after the berm is complete.