Route 109 update for the week of September 4, 2017

Route 109 update for the week of September 4, 2017

The contractor will continue cutting down the hill between Choate Park and Temple Street. A second crew will continue installing conduit for the streetlights.  A third crew will be working in front of Choate Park building stonewalls. 

An additional contractor will be installing foundations for the traffic light bases.