Route 109 update for the week of June 19, 2017
Posted on: June 16, 2017 - 10:08am
The contractor will have one crew installing drainage along Main Street and another crew removing tree stumps and prepping the front of Choate Park for the walls that will eventually be placed there.
The Fire Department will be running new fire alarm wire and Verizon will be moving wires to the new telephone poles.