Route 109 update for the week of July 31, 2017

The contractor will have one crew doing full depth reclamation starting at Lincoln Street heading toward Pond Street.  They will grind off the hot top and then dig down 21 inches, removing the soil and replacing it with good one foot thick gravel, grade it, roll and compact it, and then pave the base coat of hot top. In that area they will be cutting down the hill between Choate Park and Winthrop Street an additional 2 feet.  

There will be a second crew continuing to install catch basins and connecting them to the main drain line.