Route 109 Update for the week of December 5, 2016

Columbia Gas will be disconnecting the old main on Tuesday and Wednesday of next week.  They will start digging at Winthrop Street and Oak Street with steel plates overnight.  They will complete the work and pave on Wednesday.

The contractor will continue to install catch basins along Main Street, connecting them to the main line drainage that has been installed over the past several months.  This will have minimal impact on traffic.

Work is expected to end for the season on or around December 16th, meaning there are only 2 more weeks of Route 109 construction before breaking for winter.